The permits for the new rail terminal at Greenport Noord have been finalized. In January 2020 the construction will start of the largest domestic terminal in the Netherlands. The complex has an area of approximately 280,000 square meters and will have 900 meter tracks. The track is already connected in October. The terminal will be accessible from both east and west for trains with a maximum length of 750 meters. Trains from the west can turn to the rail terminal via a switch. For trains from the east there will be a track between the two main tracks where they can wait to cross safely. We aim to receive first train in June 2020 at the new Cabooter Railterminal Greenport Venlo.
Cabooter Railterminal Greenport Venlo
the first shovel goes into the ground
13-12-2019
The Cabooter Groep